Welcome to the RAS Solution Forums HEC-RAS Help Why all the cross section filled with water at time 00:00:00 of the simulation

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #17935
    anna pl
    Participant

    Why the profile of simulation time 00:00:00 (of an unsteady flow analysis project) appears water at the entire length of the reach?
    I use a flow hydrograph for the upstream boundary condition and normal depth for the downstream and all the cross sections of my project are
    filled with Water at time 00:00:00 (so dose the last cross section, downstream in river).
    If this happens how can i find the time that water needs to arrive at the last cross section of my river?

    (time series of the flow hydrograph starts with only 0.1 m3/s flow value)

    I would really appreciate any opinion.

    #17936
    Eric R
    Participant

    I’m not sure (I’m not very familiar with unsteady 1D simulations), but it could be an initial conditions issue. My suggestion is that you check what the associated initial conditions are.