Hi Mike, SaraA, Bryan, AGuiheux and others !
I’ve found a way to solve the same problem you encountered (1D only) : it seems be caused by the Multiple Opening Analysis conditions.
For multiple opening bridges (bridge + culvert), ONE ONLY AREA has to be set as “Conveyance”. This “Conveyance” also must be on the extreme Right or Left overbank…
Be careful to set this “Conveyance” only outside of areas where the bridge can overflow (like a weir). I solved some case in putting this “conveyance” to the far right / left of the structure (a few meters is enough).
Hope it will help you !